Example
of Stage of completion by physical completion
One
method to determine the stage of completion is physical completion. Under this
method stage of completion is calculated work completed at the end of year as
proportion to total work to be completed. The following examples will explain
this concept in depth.
Example
# 1
ABC Company is constructing a road of 500 km, the
construction details are given as under
Road
Length
|
500
Km
|
Cost
incurred to date
|
200
Million
|
Road
constructed at year end
|
200
Km
|
Period
of contract
|
2
Years
|
Contract
Price
|
$
60 million
|
Calculate
Stage of Completion by physical completion
|
|
Solution
Road
Length
|
500
Km
|
Completed
Road
|
200
Km
|
Stage of completion (200 Km / 500 Km)
x 100
|
40%
|
|
|
Example
# 2
XYZ & Company is building housing schemes of 100
houses for residential purposes. The contract detail are given below
Contract
Price for construction of 100 Houses
|
200
Million
|
Cost
incurred at the year end
|
50 Million
|
House
constructed at year end
|
25
Houses
|
Contract
completion period
|
4
Years
|
Calculate
stage of completion by physical method
|
?
|
|
|
Solution
Total
House to be Constructed
|
100
|
Houses
constructed to data
|
25
|
Stage of completion ( 25 Houses/ 100
Houses)
|
25%
|